A14: new MIT inspection on the Cerrano viaduct

New inspection by the Ministry of Infrastructure and Transport on the A 14 motorway to verify the progress of the seismic safety works and the stabilization of the landslide slope of the Cerrano viaduct.

The technical management of MIT in collaboration with the University of Chieti this morning was able to verify the validity of the interventions carried out up to now and made necessary, in recent months, to contain those landslides that threatened the stability of the structure and the safety of traffic .

Today about 80 percent of the draining trenches are completed as well as 48 anti-slip bars, interventions aimed at improving the seismic response of the structure.

A14: new MIT inspection on the Cerrano viaduct

| NEWS ' |